Type of Project
Beam & Lagging for Basement
Purpose of Piling
Temporary Shoring
Equipment Used
ABI TM 22
Installation of 788 LF of beam shoring with one row of tiebacks and 12,000 SF of 3”x12” wood lagging for a basement. The cut depths varied up to 20 ft below ground surface.
Our Commitment
Since 2010, BIFS has become the US leader of sheet pile installation utilizing the Giken Silent Piler, a unique non-vibratory, non-percussive piling machine. BIFS has completed 200+ projects with over 200,000 lf of sheet pile installation using the Giken Silent Piler. We pride ourselves on project quality, performance & ensuring that our client’s needs are met.